Strengthening a roadside ditchRussia, Krasnoyarsk Krai
In this project, a roadside ditch on the Kuznetsovo–Zykovo road was repaired and strengthened to prevent the drainage ditch from being destroyed by storm water. Work was carried out at +12 °C in the rain. A crew of 4 laid CCT2 (CC8) in 2 hours, including preparation and surface hydration. After 24 hours, the ditch had an erosion-resistant lining. A crane-manipulator was used to unroll the Concrete Canvas rolls.